2018

Info
iconfalse
title2018-12-04 BoM regular data processing start

The production archiving  of BoM global model outputs has started from the 27th November 2018 onwards.


Info
iconfalse
title2018-11-14 Current project status
Data acquisition
  • 9 model outputs archived operationally
  • 3 more test model outputs in good progress
  • 6 remaining datasets from 18 expected  without any test data yet

Verification

  • 2 models verified operationally
  • 2-3 months of regular data provision needed  to compute scores from more recently added datasets

...

Info
iconfalse
title2018-11-02 ECCC regular data processing start

The production archiving  of ECC ECCC data has started from the 2nd November 2018 onwards.

...