When the node becomes complete it will be queued immediately. This means that the suite will never complete, and output is not directly accessible through ecflowview GUI
If tasks abort, ecFlow will not schedule it again. Also if the time the job takes to complete is longer than the interval a "slot" is missed, e.g. cron 10:00 20:00 01:00 if the 10:00 run takes more than an hour the 11:00 run will never occur.
With cron you can also specify weekdays, day of the month and month of the year masks

Code Block
cron -w <weekdays> -d <days> -m <months> <start_time> <end_time> <increment> 
# weekdays:   range [0...6], Sunday=0, Monday=1, etc       e.g. -w, 0,3,6
# days:       range [1..31]                                e.g. -d 1,2,20,30    if the month does not have a day, i.e. February 21st it is ignored
# months:     range [1..12]                                e.g. -m 5,6,7,8
# start_time: The starting time(compulsory) format hh:mm  e.g. 15:21
# end_time:   The end time, if multiple times used (optional)
# increment:  The increment in time if multiple times are given(optional, however if end_time is specified then the increment must be specified