This is work in progress. More information will be added as soon as it becomes available. To get notified of any changes to this page, please log in and click on in the upper right.




Panel
borderColorblue
bgColorwhite
borderStylesolid

NEWS!

Decommission of ecgate service in Reading

Cycle 47r3 has been implemented on the Atos systems in Bologna, starting with today's 06 UTC run

Update of migration plan

24/7 support from 1 October

Update of migration plan

Update of migration timeline

Announcement of migration timeline 


Migration plan

The new Atos will not only replace the current HPC service provided by the Cray XC40 systems, but also all Linux servers, e.g. ecgate.

All users are invited to migrate their workload to the Atos at their earliest convenience. Before starting any migration work users are encouraged to familiarise themselves with the Atos HPCF and ECGATE services.

The Atos system, is still awaiting formal acceptance but is providing a full parallel service, reliably supporting the running of the Release Candidate Phase.  As we are getting closer to the switch of the operational forecast to the Atos, expected for 18 October 2022, the support level will be heightened to 24/7 from 1 October. From 1 November usage of the operational Atos HPC service (hpc-login) will be charged against SBU allocations. In the meantime Atos usage can already be monitored. The Atos ECS service (ecs-login) which replaces ecgate will remain free of charge.

  • After 31 October the Cray HPCF and all attached filesystems will no longer be available. The Cray will be immediately shutdown by the vendor and users must copy all files they need to keep to the Atos before that date.
  • From 1 November a full general user service on ecgate will no longer be available. All users are urged to migrate their activities as early as possible and copy all files still needed to the Atos before that date.
  • A reduced ecgate service will still be available from 1 November until 13 December, mainly to run TC1 activities. As ECMWF’s focus is on the systems in Bologna, ecgate will only be supported on a least-effort basis.

To support users with their migration we are offering Atos expert sessions. Please see the event page for more details and to register. 

Indicative timeline

Since 1 Oct the Atos is supported 24/7. The start of the Atos contract is currently expected for 1 November 2022. The decommissioning of the Reading data centre will start on 1 November 2022. 

Roadmap Planner
maplinks
timelinetrue
pagelinks
source%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222022-07-01%2000%3A00%3A00%22%2C%22endDate%22%3A%222022-12-31%2000%3A00%3A00%22%2C%22displayOption%22%3A%22MONTH%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Reading%22%2C%22color%22%3A%7B%22lane%22%3A%22%233b7fc4%22%2C%22bar%22%3A%22%236c9fd3%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222022-05-23%2017%3A06%3A32%22%2C%22id%22%3A%224e06d52e-c3d5-4f0c-b314-fb460f127786%22%2C%22title%22%3A%22Cray%20HPCF%22%2C%22description%22%3A%22%22%2C%22duration%22%3A5.267326732673268%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222022-11-01%2014%3A15%3A26%22%2C%22id%22%3A%22be91ce07-e4ad-4b06-a14c-5dc5da4fd319%22%2C%22title%22%3A%22reduced%20ecgate%20service%22%2C%22description%22%3A%22reduced%20ecgate%20service%C2%A0will%20be%20available%20from%201%20November%20until%2013%20December%22%2C%22duration%22%3A1.4356435643564356%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222022-07-01%2007%3A21%3A58%22%2C%22id%22%3A%222b14c60e-b090-4997-9d83-73186350207b%22%2C%22title%22%3A%22ecgate%22%2C%22description%22%3A%22%22%2C%22duration%22%3A4%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Atos%20%2F%20Bologna%22%2C%22color%22%3A%7B%22lane%22%3A%22%23ea632b%22%2C%22bar%22%3A%22%23ef8a60%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222022-11-01%2007%3A07%3A43%22%2C%22id%22%3A%228bcaae28-6084-48f1-bae1-3f4c27c43ce0%22%2C%22title%22%3A%22Operational%20service%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.217821782178218%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222022-07-21%2013%3A32%3A40%22%2C%22id%22%3A%22d8fcf281-b5d3-4394-afc3-f310ed5ecbfc%22%2C%22title%22%3A%22Parallel%20run%22%2C%22description%22%3A%22From%201%20Oct%20the%20Atos%20is%20supported%2024%2F7.%22%2C%22duration%22%3A3.366336633663366%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222022-04-30%2009%3A44%3A33%22%2C%22id%22%3A%2237d0e81d-11e8-40e2-adf7-ab028b192cf2%22%2C%22title%22%3A%22Operational%20test%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.00990099009901%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Marker%201%22%2C%22markerDate%22%3A%222021-10-15%2000%3A00%3A00%22%7D%2C%7B%22markerDate%22%3A%222022-11-01%2007%3A07%3A43%22%2C%22title%22%3A%22Start%20of%20Atos%20contract%22%7D%5D%7D
titleRoadmap%20Planner
hash45e94bbc22763221bfc801da5e8e9998