Specification of the input data:

  • Data format: WMO-GRIB2

  • Time step frequency: 3h (cumulated parameters will be not archived at step 0)

  • Grid: original model grid

  • Parameters: parameters listed below (most of them are so called High Priority according to the TIGGE-LAM project plan)

  • Model runs:  up-to 4 of all available with preference for the ones from the main forecast times (00, 06, 12, 18UTC)
  • Forecast types: perturbed, control (if available)
  • Static fields (orography, land-sea mask) are archived only for step 0 and control forecast (if exists) or the first perturbed forecast

...

High Priority parameters:

parameterAbbr.LevelUnits

TIGGE GRIB2

specification

GRIB2

paramId

type (3)

Perturbed fields provided at 3-h interval (including step 0)

10m U-velocity10u10mm s-1link165HP
10m V-velocity10v10mm s-1link166HP

Convective available potential energy

capesurfaceJ kg-1link59 

Convective inhibition

cinsurfaceJ kg-1link228001 
Mean sea level pressuremslpMSLPalink151HP

Surface air temperature

2t

1.25-2mKlink167HP

Surface air dew point temperature

2d1.25-2mKlink168HP

Perturbed fields provided at 3-h interval (excluding step 0)

Total precipitation (liquid + frozen) (4)

tpsurfacekg m-2link228228HP

Large scale precipitation (1) (4)

lspsurfacekg m-2link3062HP
10 metre wind gust in the last 3 hours (1)10fg310mm s-1link228028HP

Fields provided at step 0 (static or perturbed) (2)

Orography

(Geopotential height at the surface)

orogsurfacegpmlink228002HP

Land-sea mask

lsmsurface

proportion

(0-1 values)

link172HP

(1) Newly introduced parameters which are not stored in TIGGE (global) archive.

(2) If control forecast exists the field should be provided with it otherwise with the 1st ensemble member, always only at step 0. If the fields are perturbed there should be provided with every ensemble member, and control forecast if exists, at step 0.

(3) HP = High Priority parameter according to TIGGE-LAM expert team plans