The idea is that the variable given is advanced when the node completes and the node is re-queued (except, of course, when the variable has the last value.)
Day repeats are only available for a suite (tied to the clock) in which case an ending date can be given. For this to work the clock type must be hybrid: a real-time suite cannot be stopped by means of end time.
Code Block |
---|
repeat string INPUT str1 str2 str3
repeat integer HOUR 6 24 6
repeat date YMD 20200130 20200203 |
Note: Only four-digit years are allowed. Also, that force complete will only force the current running job to be complete, but if the repetition is not finished, the next job will be sent (with the variable advanced accordingly.)
Tip: we prefer to use the repeat date structure in our suites. This allows us to see more easily what date the suite is running.