Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Table of Contents
styleNone

1. Forecast system version

System name: GloSea5-GC2-LI

First operational forecast run:  2 April 2019

2. Configuration of the forecast model

Is it a coupled model?  Yes: Atmosphere, land, ocean and sea-ice.

...

The coupled model Global Coupled 2 (GC2) is described in Williams et al, 2015.

2.1 Atmosphere and land surface

Model

Met Office Unified Model (UM) - Global Atmosphere 6.0

Joint UK Land Environment Simulator (JULES) - Global Land 6.0

Horizontal resolution and gridN216: 0.83 degrees x 0.56 degrees (approx 60km in mid-latitudes)
Atmosphere vertical resolution85 levels
Top of atmosphere85km
Soil levels

4

Level 1 : 0 - 0.1 m

Level 2 : 0.1 - 0.35

Level 3 : 0.35 - 1.0 m

Level 4 : 1.0 - 3.0 m

Time step15 minutes

...

Global Atmosphere 6.0 & Global Land 6.0: Walters et al, 2017


2.2 Ocean and cryosphere

Ocean model

NEMO v3.4 - Global Ocean 5.0

Horizontal resolutionORCA 0.25
Vertical resolutionL75
Time step22.5 minutes
Sea ice modelCICE v4.1 - Global Sea-Ice 6.0
Sea ice model resolutionORCA 0.25
Sea ice model levels5 categories + open water
Wave modelN/A
Wave model resolutionN/A

...

Global Sea Ice 6.0: Rae et al, 2015.

3. Initialization and initial condition (IC) perturbations

3.1 Atmosphere and land


HindcastForecast
Atmosphere initialization
ERA-InterimMet Office Global Hybrid 4D-VAR
Atmosphere IC perturbationsNoneNone
Soil moisture & temperature  initializationMet Office JULES-JRA55 analysisMet Office JULES-JRA55 analysis
Snow initialization

 Met Office JULES-JRA55 analysis

Met Office JULES-JRA55 analysis
Unperturbed control forecast?NoNo

...

Met Office Global Hybrid 4D-VAR: Clayton et al, 2013


3.2 Ocean and cryosphere


HindcastForecast
Ocean initializationGloSea Ocean Sea-Ice Analysis (GS-OSIA)Forecast Ocean Assimilation Model (FOAM)
Ocean IC perturbationsNoNo
Unperturbed control forecast?NoNo

...

The common NEMOVAR system is described in Blockley et al, 2014. Details of the GS-OSIA can be found in MacLachlan et al, 2015.


4. Model uncertainties perturbations:

Model dynamics perturbationsNone
Model physics perturbationsAtmosphere stochastic physics scheme, SKEB2

If there is a control forecast, is it perturbed?

No control

...

SKEB2: Bowler et al, 2009


5. Forecast system and hindcasts


Forecast frequencydaily
Forecast ensemble size2 per day
Hindcast years24 (1993-2016)
Hindcast ensemble size7 per start date
Hindcast start dates1, 9, 17, 25 of each month
On-the-fly or static hindcast set?on-the-fly


6. Where to find more information


GloSea5 system:

...