The planned timetable for the implementation of the cycle 47r2 47r3 is as follows:

DateEvent
TBCAnnouncement of expected implementation date
5 Oct 2021

Implementation

...

  • Introduction of linear chemistry for NOx in minimization (tangent linear and adjoint code)
  • Updated background error statistics based on a more recent version of the model

Observations

  • Introduction of Sentinel-5p NO2
  • Monitoring of VIIRS AOD
  • Monitoring of Sentinel-3/SLSTR AOD

Emissions

  • Spatial smoothing applied to NO emission field in a limited area of Central Asia to eliminate numerical artefacts

Other model changes

Impact of the new cycle

A comprehensive evaluation report of the 47r3 e-suite will be made available closer to the implementation date, documenting all the changes and their impact on the forecasts. 

...

There are no new or discontinued parameters in the disseminated data compared to 47r147r2.

Software

Availability of test data from the cycle

...

47r3 test suites

Test data will become available in August.

...