Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

The page will be updated as required. It was last changed on 2112.0304.2018.

For a record of changes made to this page please refer to  Document versions.

...

The planned timetable for the implementation of the cycle IFS Cycle 45r1 is as follows:

DateEvent

21.03.2018

Initial Publication
April 2018Initial announcement, with test data in MARS
May 2018Availability of test data in dissemination
5 June 2018

Expected date of implementation

The timetable represents current expectations and may change in light of actual progress made.

Current Status

The Alpha testing of cycle 45r1 will continue and the cycle is being passed to the Forecast Department to start the Beta testingWe have now entered the Beta testing phase of IFS Cycle 45r1. We are running the new cycle in 'catch-up' mode and will shortly reach real-time. HRES and ENS test data are available in MARS.

Meteorological content of the new cycle

...

The following evaluation of the new cycle is based on the alpha testing. Scorecards will be made available based on the beta testing phase of the new cycle are now available.

Upper-air

The new cycle leads to improvements in HRES upper-air fields. Verified against the model analysis, a positive signal is seen throughout the troposphere for most parameters, except temperature in the lower troposphere at shorter ranges. The latter is mainly a result of changes to the analysis, as confirmed by corresponding neutral results against observations. Upper-air improvements are more pronounced in the tropics, especially for wind and temperature. Verified against observations, upper-air changes are overall positive in the tropics except for relative humidity, and neutral to slightly positive in the extratropics. Upper-air results for the ENS verified against analysis are mostly positive in the tropics but more neutral in the extratropics. The negative signal for temperature in the lower troposphere at shorter lead times is again mainly due to changes in the analysis. Against observations, results are mostly negative in the extratropics at early lead times and significantly positive in the tropics, with the exception of relative humidity at 700hPa. The negative impact in the extratropics is partly due to a slight reduction in ensemble spread associated with the transition to a physically more realistic SPPT scheme. Whether or not this reduced spread is genuinely detrimental depends on whether observation errors are taken into account in the verification which has not been done routinely so far. Experimental verification against radiosonde data that takes observation error into account indicates that a large fraction of the negative ENS results disappear or become statistically non-significant.

...

There is an overall improvement in 2m temperature both in the HRES and ENS, particularly for Europe. 2m humidity is largely neutral for HRES, but positive for ENS, particularly in the tropics. 10 m wind speed is largely neutral in the HRES and slightly negative in the ENS. Precipitation in the HRES is improved in terms of categorical verification (e.g. SEEPS), and near-coastal precipitation in warm-rain dominated situations is significantly improved due to changes in the cloud physics. However, these changes also lead to more activity at higher precipitation rates in active regions such as the East Asian monsoon, and as a result error measures such as RMSE or CRPS (for the ENS) are increased. The negative signal for significant wave height against analysis is a result of changes to the analysis from a large increase in observation usage, and verification against observations (buoys) shows the results are neutral for both HRES and ENS.

Tropical cyclones

The implementation of the ocean-atmosphere coupling in the HRES removes the overall negative bias in tropical cyclone central pressure and thereby reduces the mean absolute intensity error by about 10% in the short range, and about 20% from day 5 onwards. Evaluations so far show statistically neutral results for the position error.

Extended range

Changes in scores for the monthly system are generally positive across the range of parameters, with significance in week 1 for tropical winds. The only indication of a degradation is precipitation in the tropics with a consistent negative signal across all 4 weeks. There is an indication of a positive effect on skill across all parameters in the European domain. The MJO Index was significantly underspread, but changes in 45r1 to the SPPT scheme have brought the spread and error in close agreement throughout the 30 day forecast range. The underestimation of the MJO Index amplitude error has been significantly improved throughout the forecast.

...

The GRIB model identifiers (generating process identification number) for cycle 45r1 will be changed as follows:

GRIB 1
Section 1
Octets
GRIB 2
Section 4
Octets
grib_api key ComponentModel ID
OldNew
6 14  generatingProcessIdentifierAtmospheric model148149
Ocean wave model113114
HRES stand-alone ocean wave model213214

New model output parameters

Extended output have been added in cycle 45r1, including precipitation rates, CAPE indices and a total lighting lightning flash density.


paramIdShortnamenameDescriptionunitsGRIB editionComponentTest data availableDisseminationecChartsProposed for Catalogue
228050litotiInstantaneous total lightning densityTotal lightning flash density (instantaneous)flashes km-2 day-12 (TBC)

HRES / ENS

(tick)
(error)(tick)TBC(tick)
228051litotaAveraged total lightning density since previous post-processingTotal lightning flash density (averaged between consecutive post-processing time steps)flashes km-2 day-12 (TBC)
HRES / ENS
(tick)
(error)(tick)TBC
(tick)
(error)
228057litota3Averaged total lightning flash density over the past 3 hoursAveraged total (cloud-to-ground + intra-cloud) lightning flash density over the past 3 hours.flashes km-2 day-12 (TBC)
HRES / ENS
(tick)
(error)(tick)TBC(tick)
228058litota6Averaged total lightning flash density over the past 6 hoursAveraged total (cloud-to-ground + intra-cloud) lightning flash density over the past 6 hoursflashes km-2 day-12 (TBC)
HRES / ENS
(tick)
(error)(tick)TBC(tick)
260048tprateTotal precipitation rateTotal precipitation rate (instantaneous)kg m-2 s-12HRES / ENS(tick)(tick)TBC(tick)
228035mxcape6maximum CAPE in the last 6 hoursMaximum CAPE in last 6 hoursJ kg-12
HRES
(TBC)
/ ENS
(tick)
(error)(tick)TBC(tick)
228036mxcapes6maximum CAPES in the last 6 hoursMaximum
CAPESHEAR
CAPE-shear in last 6 hoursm2 s-22

HRES

(TBC)

/ ENS

(error)(tick)TBC(tick)
162071viwveVertical integral of eastward water vapour fluxVertical integral of eastward water vapour fluxkg m-1 s-11HRES / ENS(tick)(tick)TBC(tick)
162072viwvnVertical integral of northward water vapour fluxVertical integral of northward water vapour fluxkg m-1 s-11HRES / ENS(tick)(tick)TBC(tick)


Note

Due to a technical problem, parameters mxcape6 and mxcapes6 are not yet available in MARS. We also ask users not to use the new lightning data currently archived in MARS, as we are reviewing their encoding.

Software

The February 2018 Software release is suitable to handle the IFS cycle 45r1 data.

Warning

We will make a new software release shortly to allow the decoding of the new Lightning data.

ecCodes

ecCodes version 2.7.0 provides  support for the existing new model output parameters introduced in IFS Cycle 45r1. A new version of ecCodes, suitable for the new lightning parameters, will be made available shortly

GRIB API

GRIB API version 1.26.0 provides support for the existing new model output parameters introduced in IFS Cycle 45r1. A new version of GRIB API, suitable for the new lightning parameters, will be made available shortly

Note

Note that GRIB API is no longer loaded in the default user environment on the ECMWF systems. We will discontinue support for GRIB API at the end of 2018 and recommend to use ecCodes.

EMOSLIB

The version of EMOSLIB used to interpolate IFS Cycle 43r3 data is suitable to handle 45r1 data.

Note

Note that EMOSLIB is no longer loaded in the default user environment on the ECMWF systems.

Availability of test data from the IFS Cycle 45r1 test suites

Anchor
mars_data
mars_data
Test data in MARS

Test data from the IFS Cycle 45r1 test suites are available in MARS. The data are available with experiment version 0072 (MARS keyword EXPVER=0072) starting from 06 UTC on 18 March 2018.

The data can be accessed in MARS from:

Only registered users of ECMWF computing systems will be able to access the test data sets in MARS.

The data should not be used for operational forecasting.  Please report any problems you find with this data to User Support.

Test data in dissemination

IFS Cycle 45r1 test data will become available through the test dissemination system when we will have reached the release candidate stage.

Anchor
DocumentVersions
DocumentVersions
Document versions

 

DateReason for update
21.03.2018
  • Initial version
12.04.2018
  • Scorecards available
  • Impact on Tropical cyclones added
  • Test data available in MARS, with some reservation on the MXCAPE and lightning parameters.