Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Formal start of the Release Candidate Phase of the pre-operational testing. Parallel product dissemination of 41r2 test data is now available.
  • ENS and ENS-WAM days 11 to 15 will be run at the same resolution as days 0 to 10. Resolution overlap products, EFOV, will be provided from day 14 to day 15 and these will be provided for the ENS Extended only. The ENS extension to 46 days will run twice a week (Mondays and Thursdays) as before. The specific ENS calibration / validation products are discontinued.
  • A new corrected land-sea mask (LSM) was introduced for both HRES and ENS IFS 41r2 test data from 12 UTC on 9 November 2015.
  • Any changes to schedule and earlier delivery of products will be announced separately, in January 2016 at the latest.

4 November 2015

  • HRES and ENS technical test data are now available in MARS for one calendar day, together with the software needed to decode and manipulate these data. At this stage, we invite you to do some technical tests with the octahedral grid or at the lat/lon resolutions you currently use.

...