2023

Info
iconfalse
title27-06-2023 ECMWF forecast system change

New version of ECMWF IFS model (cycle 48r1) has been introduced at ECMWF since 6Z run on 2023-06-27. 

With IFS Cycle 48r1, the horizontal resolution of the  medium-range ensemble  (ENS) will increase from 18 to 9 km. This will bring the ENS to the same horizontal resolution as the high resolution forecast (HRES). The vertical resolution for both ENS and HRES will remain at 137 model levels and the ENS will continue to have 51 members. For TIGGE, the IFS data is interpolated to the same resolution O640 as up to now.

More details can be found in TIGGE model upgrades#ECMWF


Info
iconfalse
title20-01-2022 Fixed issues in KMA data

After the KMA model update on 1th of July 2022,the values of  Surface net solar radiation were wrong . Also there were some occasional unwanted zero values for some other parameters (2t, 2d, tcc, 10m u/v etc). The affected data has been fixed now.

Find more information in Issues with data.


2022

Info
iconfalse
title01-07-2022 KMA forecast system change

The KMA has changed their model used for TIGGE contribution fromUnified Model  to Korean Integrated Model ensemble (KIM), version 3.7, since the 1st  of   July 2022. Find more information in TIGGE Models.


Info
iconfalse
title30-06-2022 Meteo-France forecast system change

The last step in 18Z runs in Meteo-France contribution to TIGGE has been changed from +108 to +102 hours since    


Info
iconfalse
title04-05-2022 UKMO forecast system change

The Met Office Global model was upgraded to OS45 with effect from the 12Z cycle on 2022-05-04. Find more information in the Model upgrades page.


Info
iconfalse
title10-03-2022 TIGGE portal at CMA

The TIGGE portal at CMA should be available now again after a while in  http://tigge.cma.cn/   It should contain in principle  the same data as the TIGGE archive at ECMWF. Currently after some technical issues in the past, the data is still available only for more recent period which should be extended soon to contain more historical data too. 

2021

Info
iconfalse
title13-10-2021 ECMWF forecast system change

New version of ECMWF IFS model (cycle 47r3) has been introduced at ECMWF since 6Z run on 2021-10-12. 

Cycle upgrade 47r3 will bring improvements to the assimilation and observations usage and a significantly improved physical basis for moist processes, necessary to facilitate further development of the Integrated Forecasting System (IFS) and future application at convection-permitting resolutions.

More details can be found in

  • Implementation of IFS Cycle 47r3
  • https://www.ecmwf.int/en/publications/ifs-documentation
  • TIGGE model upgrades#ECMWF


    Info
    iconfalse
    title24-06-2021 Yearly stats added

    Yearly statistics have been added to  TIGGE usage statistics .

    ...

    Info
    iconfalse
    title12-05-2021 ECMWF forecast system change

    New version of ECMWF IFS model (cycle 47r2) has been introduced at ECMWF since 2021-05-11. In the IFS Cycle 47r2 single-precision for ENS (forecast up to day 46 and hindcast) and HRES (forecast) has been introduced. Moreover, the ENS vertical levels has been increased to 137 to bring it in line with HRES. 

    This change will not affect the format of TIGGE products from IFS. Full

    More details can be found in Implementation of IFS Cycle 47r2in TIGGE model upgrades#ECMWF


    Info
    iconfalse
    title27-04-2021 JMA forecast system change

    JMA global EPS has been upgraded to the version GEPS_2103 since   

    The major changes are:

    • Increase of the number of vertical layers from 100 to 128
    • Increase of the number of ensemble members from 27 to 51
    • Revision of the global snow analysis
    • Introduction of the global soil moisture analysis

    Further details can be found in the page  Models .  

    ...

    Info
    iconfalse
    title17-12-2020 New model ICON from DWD added to TIGGE archive

    The outputs from the global model ICON produced by Deutscher Wetterdienst (DWD) have been added to TIGGE archive starting from 12Z,  7 December 2020. In contrary to other ensemble systems, in ICON the control forecast is not produced (the ensemble consists of 40 perturbed members only). The high resolution forecast interpolated to the same resolution as the ensemble is also available for users.  Click   here   for more details.


    Info
    iconfalse
    title26-11-2020 NCEP forecast system change

    The NCEP global prediction system was upgraded to GEFS v12  since 12Z, 23 Sep 2020. The main technical changes related to TIGGE are:

    • increased ensemble size from 21 to 31
    • increased horizontal resolution from 1 to 0.5 degree

    Find more information in the page Models.

    ...

    Info
    iconfalse
    title13-07-2020 New model IMD GEFS added to TIGGE archive

    New model outputs from the Global Ensemble Forecast System (GEFS) produced by India Meteorological Department (IMD) were added to TIGGE archive starting from 1 July 2020. Users can access the data on 0.12° x  0.12° grid (~12 km).  Click  here  for more details.


    Info
    iconfalse
    title30-06-2020 ECMWF forecast system change

    The ECMWF global prediction system  was upgraded to the version 47r1  since 30 June 2020. Find more information in the Model upgrades page.

    ...

    Info
    iconfalse
    title20-12-2017 New model NCMRWF added to TIGGE archive
    New model outputs  from National Centre for Medium Range Weather Forecasting (NCMRWF, India) were added to TIGGE archive. The first starting date available thanks to the back-archiving is the 1st of August 2017. Click here for more details.


    Info
    iconfalse
    title11-07-2017 ECMWF forecast system change
    Update of ECMWF forecast system. A new version of ECMWF model (IFS cycle 43r3) was introduced. Click here for more details.


    Info
    iconfalse
    title11-07-2017 Met Office Tropical Cyclone CXML data
    From the 12UTC forecast on 11th July 2017 the Met Office tropical cyclone CXML data come from the upgraded MOGREPS-G (UM PS39) forecasts. Note that each CXML dataset includes tracks from a lagged ensemble of 36 members, i.e. the current forecast and the forecast from 6 hours earlier. The CXML data are available via the NCAR archive at  http://rda.ucar.edu/datasets/ds330.3/ or see the TIGGE cyclone exchange page at http://www.cawcr.gov.au/research/cyclone-exchange/ for further information.

    ...

    Info
    iconfalse
    title11-07-2017 Met Office forecast system change

    Update of MetOffice forecast system. A new version of MetOffice model (UM PS39) was introduced. Click here for more details.


    Info
    iconfalse
    title19-01-2017 JMA forecast system change
    Update of JMA forecast system. A new version of JMA model was introduced. Click here for more details.

    ...

    Info
    iconfalse
    title02-12-2014 TIGGE Website migration

    Please note that information from the TIGGE website is being migrated. This website is no longer being updated. The main TIGGE project page is now at http://www.ecmwf.int/en/research/projects/tigge and further details about TIGGE are available via https://confluencesoftware.ecmwf.int/wiki/display/TIGGE/Home


    Info
    iconfalse
    title06-11-2014 Met Office TIGGE data - November 2014 update

    The Met Office TIGGE data now includes data from the higher resolution, 7-day MOGREPS-G global ensemble (rather than MOGREPS-15, as used up to 00Z 15th July). The new data are being provided in near-real time from 00Z 6th November, and it is planned to back-fill the gap in due course. The new ensemble data includes 12 members run four times a day, with a reduced number of parameters. Click  here for more details.

    ...