How do I advance a REPEAT even when some of the tasks are aborted?

Step-by-step guide

There are several ways to do this.

  1. If the tasks are not very robust and are known to fail regularly then, we can have a custom ERROR trapping, which instead of aborting the task, log the aborts, and sets the task to complete. The logging could be anything

    # Defined a error handler
    ERROR() {
        echo "ERROR called"
        set +e                     # Clear -e flag, so we don't fail
        wait                       # wait for background process to stop
    
        # Record the failure in the log file for later analysis
        ecflow_client --msg="ERROR task %ECF_NAME% failed"
    
        ecflow_client --complete   # replace abort with a complete
        trap 0                     # Remove the trap
        exit 0                     # End the script
    }
  2. Have a special task whose job is to monitor failure in the other tasks. This task will then log the failures and then automatically set the family/repeat to complete.

    suite suite
      family main
        repeat date YMD 20170101 20180101 1
        task dodgy    # this task may fail
        task ok
        task fix                                          # handle failures, so repeat will advance even if other tasks fail
          complete dodgy == complete and ok  == complete  # If there are no failures, complete fix, so repeat will advance
          time 23:30                                      # run at 23:30, allowing users to address task dodgy otherwise automatically advance the REPEAT
      endfamily
    endsuite
    
    fix.ecf
    # task fix.ecf
    %include <head.h>
    
    trap 0
    ecflow_client --force=complete recursive %SUITE%/%FAMILY%
    exit 0
    
    %include <tail.h>