NEWS!

Announcement of ECPDS migration.

Transition plan

As part of our Data Centre move we have started the installation of ECPDS, the ECMWF Production Data Store, in Bologna. ECPDS, which is described in a Newsletter article, takes care of both the dissemination and acquisition of data. For the migration of the operational ECPDS we are currently considering two options: 

  1. Incremental move of individual data streams
  2. Switch-over of all data streams together with the switch-over of the operational forecast

We will confirm at a later date which option will be used.

As a first step to prepare for an operational ECPDS in Bologna we are asking providers and recipients of operational data to make changes to their network setup. We will also offer transfer tests to ensure that external hosts will be ready for the switch-over of the operational forecast production from Reading to Bologna, expected for April 2022. 

Note that the operational dissemination will continue to originate from our Reading Data Centre until its decommissioning in the second quarter of 2022.

Nov2021DecJan2022FebMarAprMayJunOperational switch-over
Operations
ECPDS

Operational forecast, Reading

Release candidate, Bologna

Operational forecast, Bologna

Transfer tests

Action required by dissemination users/sites

Please update your firewall rules at your earliest convenience, at the latest by 31 Nov 2021, to accept connections from our new IP addresses used in Bologna:

Internet:

  • 136.156.192.0/26
  • 136.156.193.0/26

RMDCN:

  • 136.156.196.0/26
  • 136.156.197.0/26

Please ensure that you keep the current firewall rules in place to allow connections from our Reading Data Centre subnets.

Between the late November 2021 and 31 March 2022 we will offer connectivity tests, involving the transfer of files named "ecmwf-tst.bol" and "ecmwf-tst.md5". Therefore, please also remove any restrictions on your side which might prevent the transfer of these files. Two weeks in advance of the planned test we will contact users with the exact test date and further details.

Action required by ECMWF data providers

Actions required by data providers that ECMWF retrieves data from or by those uploading data to ECMWF are detailed in a blog post.